We want to keep our neighbours up to date on our  construction works. All details on upcoming construction and additional works can be found here.


Works over the next quarter
14 August 2020

Works over the next quarter include:

  • the removal of the scaffolding will continue
  • the roof works will be completed
  • the louvres will be installed
  • work to the balustrading and brickwork continues
  • the internal fit-out of the laboratories and patient accommodation continues
  • the commissioning of the building continues.

The path

The path in front of the Pears Building is currently closed to allow landscaping works and installation of the louvres. Once this is complete, Willmott Dixon will allow access for council workers to undertake work to refurbish the path. This will shorten the length of time that the path is closed.

Camden anticipates the work could start late October/early November and take four to six weeks – but this is just an estimate at this stage.

Closure of path
5th Aug 2020

Hampstead Hill School’s fire evacuation procedure involves mustering pupils and staff on the path. In the event of the school needing to evacuate while the path is closed, the school will inform Willmott Dixon who will immediately suspend operations and re-open the path.

The school has been provided with a comprehensive list of contacts for the construction team to set this process in motion.

Operations would remain suspended along the path until the evacuation of the school was complete and all pupils and staff had left the footpath

Tower crane removal from Pears Building site 20 & 27 June 2020
19 Jun 2020

The removal of a tower crane from the Pears Building construction site will take place across the next two weekends, ie 20 and 27 June.

Willmott_Dixon,_Pears_Building,_The_Royal_Free_Hospital,_166B,_TC2,_Dismantle,_Drawing

PB3100_Rosslyn_Hill

PB3101_Rosslyn_Hill

Construction works, W/C 14 January 2019
28 Jan 2020

Construction works, weeks commencing 14 January 2019

Construction works, weeks commencing 7 January – 21 January 2019 
17 Jan 2019

Construction works, weeks commencing 7 January – 21 January 2019

Construction work, weeks commencing 3 December – 17 December 2018
14 Dec 2018

Construction works, weeks commencing 3 December – 17 December 2018

Construction work, weeks commencing 12 November – 26 November 2018
13 Nov 2018

Construction works, weeks commencing 12 November – 26 November 2018

Construction works, weeks commencing 29 October – 5 November 2018
25 Oct 2018

Construction works, weeks commencing 29 October – 5 November 2018

Construction works, weeks commencing 8, 15 and 22 October 2018
3 Oct 2018

Construction works, weeks commencing 8, 15 and 22 October 2018

Construction works, week commencing 27 August – 10 September 2018
3 Sep 2018

Construction works, weeks commencing 27 August – 10 September 2018

Construction works, weeks commencing 13 August – 27 August 2018
8 Aug 2018

Construction works, weeks commencing 13 August – 27 August 2018

Construction works, late July to early August 2018
25 July 2018

Construction look ahead late July to early August 2018

Construction works, weeks commencing 2, 9 and 16 July 2018
29 Jun 2018

Construction works, weeks commencing 2, 9 and 16 July 2018

Construction works, weeks commencing 4, 11 and 18 June 2018
5 Jun 2018

Construction look ahead works w/c 4 June 18

Construction works, weeks commencing 8 May 2019
25 May 2018

Construction look ahead works w/c 08.05.18

 

Contacts

Philippa Hutchinson
Interim head of communications

[email protected]

If you become aware of an urgent operational issue concerning the construction, please contact Willmott Dixon immediately on 07704 260779 (weekdays) or 08457 335533 out of hours.