Agenda CWG meeting 13 October 2020
16 Sep 2020

Agenda CWG meeting 13 October 2020

CWG meeting notes 21 July 2020
30 Jul 2020

CWG_meeting_notes_21_July_2020

Meetings are currently suspended because of the pandemic
22 Jun 2020

Tower crane removal from Pears Building site 20 & 27 June 2020
19th Jun 2020

The removal of a tower crane from the Pears Building construction site will take place across the next two weekends, ie 20 and 27 June.

The removal of a tower crane from the Pears Building construction site will take place across the next two weekends, ie 20 and 27 June.

Work will start at 7.30am and finish by 1pm, in line with permitted working hours for this project. The early start will allow road closure signage to be put in place to minimise disruption. No work on the crane will take place until 8am.

The closure of Rosslyn Hill adjacent to the Hampstead Green is necessary to remove the crane because of the size of required equipment. There will be some associated noise but we don’t expect this to be excessive. Willmott Dixon managers will be on site during the operation and happy to answer any questions you may have. You can also email me at this address.

The removal of the crane, along with the recent removal of the hoarding, mark the beginning of a milestone stage in the project. Willmotts and the charity are very grateful for the forbearance of local people during the work to date.

Willmott_Dixon,_Pears_Building,_The_Royal_Free_Hospital,_166B,_TC2,_Dismantle,_Drawing

PB3100_Rosslyn_Hill

PB3101_Rosslyn_Hill

CWG meeting notes 14 January 2020
19 Jun 2020

CWG meeting notes 14 January 2020

Pears Building newsletters

Issue 21 – September 2020

Issue 20 – July 2020

Issue 19 – May 2020

Issue 18 – March 2020

Issue 17 – January 2020

Issue 16 – November 2019

Issue 15 – September 2019

Issue 14 – July 2019

Issue 13 – May 2019

Issue 12 – March 2019

Issue 11 – January 2019

Issue 10 – December 2018

Issue 9 – October 2018

Issue 8 – August 2018

Issue 7 – June 2018

Issue 6 – April 2018

Issue 5 – February 2018

Issue 4 – November 2017

Issue 3 – October 2017

Issue 2 – July 2017

Issue 1 – June 2017

Agenda CWG meeting 14 January 2020
8 Jan 2020

Agenda CWG meeting 14 January 2020

CWG meeting notes 7 October 2019
22 Oct 2019

CWG meeting notes 7 October 2019

Agenda CWG meeting 7 October 2019
2 Oct 2019

Agenda CWG meeting 7 October 2019

CWG meeting notes 22 July 2019
2 Oct 2019

CWG meeting notes 22 July 2019

Agenda CWG meeting 22 July 2019
2 Jul 2019

Agenda CWG meeting 22 July 2019

Willmott Dixon’s short video for the induction of new construction staff
5 Jun 2019

In this video some of Willmott Dixon’s team explains why the building project is important to them. Professors Emma Morris and Lucy Walker also highlight the benefits that the new facilities will add to their research

CWG meeting notes 21 May 2019
28 May 2019

CWG meeting notes 21 May 2019

Hospital vibration report graph from w/c 1 April 2019 for 1 month
13 May 2019

Hospital vibration report graph from w/c 1 April 2019 for 1 month

Noise report graph all enviroguards from w/c 1 2019 for 1 month
13 May 2019

Noise report graph all enviroguards from w/c 1 April 2019 for 1 month

Dust report graph all enviroguards from w/c 1 April 2019 for 1 month
13 May 2019

Church vibration report graph from w/c 1 April 2019 for 1 month

Agenda CWG meeting 21 May 2019
7 May 2019

Agenda CWG meeting 25 February 2019

Photo showing building progress, 29 April 2019
29 April 2019

This photo shows construction progress as on 29 April 2019 since the completion to the below ground works.

Hospital vibration report graph from w/c 4 March 2019 for 1 month
3 April 2019

Hospital vibration report graph from w/c 4 March 2019 for 1 month

Noise report graph all enviroguards from w/c 4 March 2019 for 1 month
3 April 2019

Noise report graph all enviroguards from w/c 4 March 2019 for 1 month

Dust report graph all enviroguards from w/c 4 March 2019 for 1 month
3 April 2019

Dust report graph all enviroguards from w/c 4 March 2019 for 1 month

Church vibration report graph all enviroguards from w/c 4 March 2019 for 1 month
3 April 2019

Church vibration report graph from w/c 4 March 2019 for 1 month

School vibration report graph all enviroguards from w/c 4 March 2019 for 1 month
3 April 2019

School vibration report graph from w/c 04 March 19 for 1 month

CWG meeting notes 25 February 2019
1 March 2019

CWG meeting notes 25 February 2019

Hospital vibration report graph from w/c 18 February 2019 for 1 month
25 February 2019

Hospital vibration report graph w/c 18 February 2019

Church vibration report graph from w/c 18 February 2019 for 1 month
25 February 2019

Church vibration report graph w/c 18 February 2019

Dust report graph from w/c 18 February 2019 for 1 month
25 February 2019

Dust report graph all enviroguards w/c 18 February 2019

Noise report graph from w/c 18 February 2019 for 1 month
25 February 2019

Noise report graph all enviroguards w/c 18 February 2019

School vibration report graph from w/c 18 February 2019 for 1 month
25 February 2019

School vibration report graph w/c 18 February 2019

Dust report graph from w/c 4 February 2019 for 1 month
11 February 2019

Dust report graph all enviroguards w/c 4 February 2019

Hospital vibration graph from w/c 4 February 2019 for 1 month
11 February 2019

Hospital vibration report graph w/c 4 February 2019

Noise report graph from w/c 4 February 2019 for 1 month
11 February 2019

Noise report graph all enviroguards w/c 4 February 2019

School vibration graph from w/c 4 February 2019 for 1 month
11 February 2019

School vibration report w/c 4 February 2019

CWG meeting notes 14 January 2019
28 Jan 2020

CWG meeting notes 14 January 2019

Construction works, W/C 14 January 2019
28 Jan 2020

Construction works, weeks commencing 14 January 2019

Noise report graph from w/c 14 January 2019 for 1 month
22 Jan 2019

Noise report graph all enviroguards w/c 14 January 2019

Hospital vibration graph from w/c 14 January 2019 for 1 month
22 Jan 2019

Hospital vibration report graph w/c 14 January 2019

Church vibration graph from w/c 14 January 2019 for 1 month
22 Jan 2019

Church vibration report graph w/c 14 January 2019

Dust report graph from w/c 14 January 2019 for 1 month
22 Jan 2019

Dust report graph all enviroguards w/c 14 January 2019

School vibration graph from w/c 14 January 2019 for 1 month
22 Jan 2019

School vibration report w/c 14 January 2019ol_Vibration_Report_Graph_wc14Jan19

Noise report graph from w/c 7 January 2019 for 1 month
22 Jan 2019

Noise report graph all enviroguards w/c 7 January 2019

Hospital vibration graph from w/c 7 January 2019 for 1 month
22 Jan 2019

Hospital vibration report graph w/c 7 January 2019

Church vibration graph from w/c 7 January 2019 for 1 month
22 Jan 2019

Church vibration report graph w/c 7 January 2019

Dust report graph from w/c 7 January 2019 for 1 month
22 Jan 2019

Dust report graph all enviroguards w/c 7 January 2019

School vibration graph from w/c 7 January 2019 for 1 month
22 Jan 2019

School vibration report w/c 7 January 2019

Construction works, weeks commencing 7 January – 21 January 2019 
17 Jan 2019

Construction works, weeks commencing 7 January – 21 January 2019

Agenda CWG meeting 14 January 2019
3 Jan 2019

Agenda CWG meeting 14 January 2019

Hospital vibration graph from w/c 10 December 2018
19 Dec 2018

Hospital vibration report graph w/c 10 December 2018

Noise report graph from w/c 10 December 2018
19 Dec 2018

Noise report graph all enviroguards w/c 10 December 2018

Dust report graph from w/c 10 December 2018
19 Dec 2018

Dust report graph all enviroguards w/c 10 December 2018

Church vibration report from w/c 10 December 2018
19 Dec 2018

Church vibration report graph w/c 10 December 2018

School vibration report from w/c 10 December 2018
19 Dec 2018

School vibration report w/c 10 December 2018

CWG meeting notes 3 December 2018
17 Dec 2018

CWG meeting notes 3 December 2018

Hospital vibration report graph from w/c 26 November 2018
14 Dec 2018

Hospital vibration report graph w/c 26 November 2018

Noise report graph all enviroguards from w/c 26 November 2018
14 Dec 2018

Noise report graph w/c 26 November 2018

Dust report graph all enviroguards from w/c 26 November 2018
14 Dec 2018

Dust report graph all enviroguards w/c 26 November 2018

Church vibration report graph from w/c 26 November 2018
14 Dec 2018

Church vibration report graph w/c 26 November 2018

School vibration report graph from w/c 26 November 2018
14 Dec 2018

School vibration report w/c 26 November 2018

Pears ground monitoring review, 16 Nov – 30 Nov 2018
14 Dec 2018

Pears Ground Monitoring Review, 16 Nov – 30 Nov 2018

Extended Saturday Working Saturday 12 January 2019
14 Dec 2018

Extended Saturday Working Saturday 12 January 2019

Construction work, weeks commencing 3 December – 17 December 2018
14 Dec 2018

Construction works, weeks commencing 3 December – 17 December 2018

Hospital vibration report graph from w/c 5 November 2018
30 Nov 2018

Hospital vibration report graph w/c 5 November 2018

Noise report graph all enviroguards from w/c 5 November 2018
30 Nov 2018

Noise report graph all enviroguards w/c 5 November 2018

Dust report graph all enviroguards from w/c 5 November 2018
30 Nov 2018

Dust report graph all enviroguards w/c 5 November 2018

Church vibration report graph from w/c 5 November 2018
30 Nov 2018

Church vibration report graph w/c 5 November 2018

School vibration report graph from w/c 5 November 2018
30 Nov 2018

School vibration report w/c 5 November 2018

Construction work, weeks commencing 12 November – 26 November 2018
13 Nov 2018

Construction works, weeks commencing 12 November – 26 November 2018

Agenda CWG meeting 3 December 2018
13th Nov 2018

Agenda CWG meeting 3 December 2018

Hospital vibration report graph from w/c 29 October 2018
8 Nov 2018

Hospital vibration report graph w/c 29 October 2018

Noise report graph all enviroguards from w/c 29 October 2018
8 Nov 2018

Noise report graph all enviroguards w/c 29 October 2018

Dust report graph all enviroguards from w/c 29 October 2018
8 Nov 2018

Dust report graph all enviroguards w/c 29 October 2018

School vibration report graph from w/c 29 October 2018
8 Nov 2018

School vibration report w/c 29 October 2018

Church vibration report graph from w/c 29 October 2018
8 Nov 2018

Church vibration report graph w/c 29 October 2018

Hospital vibration report graph from w/c 22 October 2018
8 Nov 2018

Hospital vibration report graph w/c 22 October 2018

Noise report graph all enviroguards from w/c 22 October 2018
8 Nov 2018

Noise report graph all enviroguards w/c 22 October 2018

Church vibration report graph from w/c 22 October 2018
8 Nov 2018

Church vibration report graph w/c 22 October 2018

Dust report graph all enviroguards from w/c 22 October 2018
8 Nov 2018

Dust report graph all enviroguards w/c 22 October 2018

School vibration report graph from w/c 22 October 2018
8 Nov 2018

School vibration report w/c 22 October 2018

CWG meeting notes 22 October 2018
2 Nov 2018

CWG meeting notes 22 October 2018

Hampstead Hill School – Manual Structural Monitoring Data 1 January 2018 – 23 October 2018
1 Nov 2018

Hampstead Hill School – Manual Structural Monitoring Data 1 January 2018 – 23 October 2018

Inclinometer Readings – 12 March 2018 for 33 weeks
1 Nov 2018

Inclinometer Reading 12 March 2018 for 33 weeks

Construction works, weeks commencing 29 October – 5 November 2018
25 Oct 2018

Construction works, weeks commencing 29 October – 5 November 2018

Noise report graph all enviroguards from w/c 15 October 2018
25 Oct 2018

Noise report graph all enviroguards w/c 15 October 2018

Hospital vibration report graph from w/c 15 October 2018
25 Oct 2018

Hospital vibration report graph w/c 15 October 2018

Church vibration report graph from w/c 15 October 2018
25 Oct 2018

Church vibration report graph w/c 15 October 2018

Dust report graph all enviroguards from w/c 15 October 2018
25 Oct 2018

Dust report graph all enviroguards w/c 15 October 2018

School vibration report graph from w/c 15 October 2018
25 Oct 2018

School vibration report w/c 15 October 2018

Dust report graph all enviroguards from w/c 8 October 2018
25 Oct 2018

Dust report graph all enviroguards w/c 8 October 2018

Noise report graph all enviroguards from w/c 8 October 2018
25 Oct 2018

Noise report graph all enviroguards w/c 8 October 2018

Hospital vibration report graph from w/c 8 October 2018
25 Oct 2018

Hospital vibration report graph w/c 8 October 2018

School vibration report graph from w/c 8 October 2018
25 Oct 2018

School vibration report w/c 8 October 2018

Church vibration report graph from w/c 8 October 2018
25 Oct 2018

Church vibration report graph w/c 8 October 2018

Hospital vibration report graph from w/c 1 October 2018
25 Oct 2018

Hospital vibration report graph w/c 1 October 2018

Dust report graph all enviroguards from w/c 1 October 2018
25 Oct 2018

Dust report graph all enviroguards w/c 1 October 2018

Noise report graph all enviroguards from w/c 1 October 2018
25 Oct 2018

Noise report graph all enviroguards w/c 1 October 2018

Church vibration report graph from w/c 1 October 2018
25 Oct 2018

Church vibration report graph w/c 1 October 2018

School vibration report graph from w/c 1 October 2018
25 Oct 2018

School vibration report w/c 1 October 2018

Hospital vibration report graph from w/c 24 September 2018
25 Oct 2018

Hospital vibration report graph w/c 24 September 2018

Dust report graph all enviroguards from w/c 24 September 2018
25 Oct 2018

Dust report graph all enviroguards w/c 24 September 2018

Noise report graph all enviroguards from w/c 24 September 2018
25 Oct 2018

Noise report graph all enviroguards w/c 24 September 2018

School vibration report graph from w/c 24 September 2018
25 Oct 2018

School vibration report w/c 24 September 2018

Church vibration report graph from w/c 24 September 2018
25 Oct 2018

Church vibration report graph w/c 24 September 2018

Hospital vibration report graph from w/c 17 September 2018
25 Oct 2018

Hospital vibration report graph w/c 17 September 2018

Noise report graph all enviroguards from w/c 17 September 2018
25 Oct 2018

Noise report graph all enviroguards w/c 17 September 2018

Church vibration report graph from w/c 17 September 2018
25 Oct 2018

Church vibration report graph w/c 17 September 2018

Dust report graph all enviroguards from w/c 17 September 2018
25 Oct 2018

Dust report graph all enviroguards w/c 17 September 2018

School vibration report graph from w/c 17 September 2018
25 Oct 2018

School vibration report w/c 17 September 2018

Agenda CWG meeting 22 October 2018
5 Oct 2018

Agenda CWG meeting 22 October 2018

Construction works, weeks commencing 8, 15 and 22 October 2018
3 Oct 2018

Construction works, weeks commencing 8, 15 and 22 October 2018

CWG meeting notes 17 September 2018
1 Oct 2018

CWG meeting notes 17 September 2018

Movement monitoring reports
14 Sep 2018

These reports must be read in conjunction with the detailed basement construction plan, particularly the monitoring action plan contained within it.

Movement monitoring report 12 September 2018

Movement monitoring report 12 August 2018

Movement monitoring report 2 August 2018

Movement monitoring report 13 July 2018

Noise report graph all enviroguards from w/c 3 September 2018
14 Sep 2018

This environmental report recorded between 3 and 10 September shows that the only issue of note relates to noise and the cause. These works have since been completed

Noise report graph all enviroguards w/c 3 September 2018

Dust report graph all enviroguards from w/c 3 September 2018
14 Sep 2018

Dust report graph all enviroguards w/c 3 September 2018

Church vibration report graph from w/c 3 September 2018
14 Sep 2018

Church vibration report graph w/c 3 September 2018

School vibration report graph from w/c 3 September 2018
14 Sep 2018

School vibration report w/c 3 September 2018

Hospital vibration report graph from w/c 3 September 2018
14 Sep 2018

Hospital vibration report graph w/c 3 September 2018

Construction works, week commencing 27 August – 10 September 2018
3 Sep 2018

Construction works, weeks commencing 27 August – 10 September 2018

Agenda CWG meeting 17 September 2018
3 Sep 2018

Agenda CWG meeting 17 September 2018

Church vibration report graph from w/c 13 August 2018
22 Aug 2018

Church vibration report graph w/c 13 August 2018

Noise report graph all enviroguards from w/c 13 August 2018
22 Aug 2018

Noise has been the predominant issue during this period due to the activities taking place on the site, including the demolition of the car park, removal of obstructions beneath ground level and the excavation of excess material. We expect the removal of the latter to be complete by the end of the school holidays.

Noise report graph all enviroguards w/c 13 August 2018

School vibration report graph from w/c 13 August 2018
22 Aug 2018

School vibration report w/c 13 August 2018

Dust report graph all enviroguards from w/c 13 August 2018
22 Aug 2018

Dust report graph all enviroguards w/c 13 August 2018

Church vibration report graph from w/c 6 August 2018
22 Aug 2018

Church vibration report graph w/c 6 August 2018

School vibration report graph from w/c 6 August 2018
22 Aug 2018

School vibration report w/c 6 August 2018

Hospital vibration report graph from w/c 6 August 2018
22 Aug 2018

Hospital vibration report graph w/c 6 August 2018

Noise report graph all enviroguards from w/c 6 August 2018
22 Aug 2018

Noise report graph all enviroguards w/c 6 August 2018

Dust report graph all enviroguards from w/c 6 August 2018
22 Aug 2018

Dust report graph all enviroguards w/c 6 August 2018

CWG meeting notes 24 July 2018
9 Aug 2018

CWG meeting notes 24.07.18

Construction works, weeks commencing 13 August – 27 August 2018
8 Aug 2018

Construction works, weeks commencing 13 August – 27 August 2018

Monitoring and the Pears Building
7 Aug 2018

The Pears Building and the neighbourhood

A new home for the UCL Institute of Immunity and Transplantation (IIT), which has been operating within the Royal Free Hospital since 2013, is being created in the Pears Building, with the help of a £5 million donation by the Pears Foundation, a family charity based in Hampstead.

Designed by the internationally recognised Hopkins Architects, the new facilities will provide over 6,000m² of the best possible infrastructure for research, training and clinical care. There will be the most modern laboratories, modern equipment and patient accommodation. The Pears Building will also house the Royal Free Charity and its team of volunteers.

During construction, which will be complete in 2020, the charity and the builder, Willmott Dixon, are working hard to minimise the impact of the process on the surrounding area.

A number of environmental monitors have been installed around the site to monitor the effects of dust, vibration and noise on the immediate neighbours, which include St Stephen’s Church and Hampstead Hill School.

Permitted thresholds have been agreed with Camden Council and the site is being constantly monitored against these. Results are regularly reported to a construction working group, which includes representatives of the church and school and local residents, and uploaded to the Royal Free Charity website. The website also contains a wealth of other information about the construction process.

Willmott Dixon is an associate member of the Considerate Constructor Scheme and is committed to:

  • ensuring the site appears professional and is well managed
  • giving utmost consideration to the projects impact on neighbours and the public
  • protecting and enhance the environment
  • seeking sustainable solutions, and minimise waste, the projects carbon footprint and resources
  • attaining the highest levels of safety performance
  • providing a supportive and caring working environment

The scheme involves third party inspections of the site, workforce and the impact of the project on the community.

Noise report graph all enviroguards from w/c 30 July 2018
7 Aug 2018

Noise report graph all enviroguards w/c 30 July 2018

Dust report graph all enviroguards from w/c 30 July 2018
7 Aug 2018

Dust report graph all enviroguards w/c 30 July 2018

Church vibration report graph from w/c 23 July 2018
7 Aug 2018

Church vibration report graph w/c 23 July 2018

School vibration report graph from w/c 23 July 2018
7 Aug 2018

School Vibration Report w/c 23 July 2018

Hospital vibration report graph from w/c 23 July 2018
7 Aug 2018

Hospital vibration report graph w/c 23 July 2018

Noise report graph all enviroguards from w/c 23 July 2018
7 Aug 2018

Noise report graph all enviroguards w/c 23 July 2018

Dust report graph all enviroguards from w/c 23 July 2018
7 Aug 2018

Dust report graph all enviroguards w/c 23 July 2018

Pears Building planning applications
25 July 2018

The building currently under construction has planning permission from Camden Council. But from time to time supplementary applications will be made in order to fulfil various conditions which have been applied to the project by the council. These may lead to minor alternations which must be approved by the council.

As we become aware that these are necessary, we will keep you informed via this website.

Construction works, late July to early August 2018
25 July 2018

Construction look ahead late July to early August 2018

Church vibration report graph from w/c 9 July 2018
19 Jul 2018

Church vibration report graph w/c 9 July 2018

School vibration report graph from w/c 9 July 2018
19 Jul 2018

School Vibration Report w/c 9 July 2018

Hospital vibration report graph from w/c 9 July 2018
19 Jul 2018

Hospital vibration report graph w/c 9 July 2018

Noise report graph all enviroguards from w/c 9 July 2018
19 Jul 2018

Noise report graph all enviroguards w/c 9 July 2018

Dust report graph all enviroguards from w/c 9 July 2018
19 Jul 2018

Dust report graph all enviroguards w/c 9 July 2018

Church vibration report graph from w/c 2 July 2018
19 Jul 2018

Church vibration report graph w/c 2 July 2018

Noise report graph all enviroguards from w/c 2 July 2018
19 Jul 2018

Noise report graph all enviroguards w/c 2 July 2018

Hospital vibration report graph from w/c 2 July 2018
19 Jul 2018

Hospital vibration report graph w/c 2 July 2018

Dust report graph all enviroguards from w/c 2 July 2018
19 Jul 2018

Dust report graph all enviroguards w/c 2 July 2018

Church vibration report graph from w/c 18 June 2018
6 Jul 2018

Church vibration report graph w/c 18 June 2018

Hospital vibration report graph from w/c 18 June 2018
6 Jul 2018

Hospital vibration report graph w/c 18 June 2018

Noise report graph all enviroguards from w/c 18 June 2018
6 Jul 2018

Noise report graph all enviroguards w/c 18 June 2018

Dust report graph all enviroguards from w/c 18 June 2018
6 Jul 2018

Dust Report Graph all enviroguards w/c 18 June 2018

Hoarding for Pears Building site
6 Jul 2018

Hoarding plan for Pears Building

Construction works, weeks commencing 2, 9 and 16 July 2018
29 Jun 2018

Construction works, weeks commencing 2, 9 and 16 July 2018

CWG meeting notes 26 June 2018
26 Jun 2018

CWG meeting notes 26 June 2018

Church vibration report graph w/c 11 June 2018
18 Jun 2018

Church Vibration Report Graph w/c 11 June 2018

Hospital vibration report graph w/c 11 June 2018
18 Jun 2018

Hospital vibration report graph w/c 11 June 2018

Noise report graph all enviroguards w/c 11 June 2018
18 Jun 2018

Noise report graph all enviroguards w/c 11 June 2018

Dust report graph all enviroguards w/c 11 June 2018
18 Jun 2018

Dust Report Graph all enviroguards w/c 11 June 2018

Church vibration report graph w/c 4 June 2018
12 Jun 2018

Church Vibration report graph w/c 4 June 2018

Hospital vibration report graph w/c 4 June 2018
12 Jun 2018

Hospital vibration report graph w/c 4 June 2108

Noise report graph all enviroguards w/c 4 June 2018
12 Jun 2018

Noise report graph all enviroguards w/c4 June 2018

Dust report graph all enviroguards w/c 4 June 2018
12 Jun 2018

Dust Report Graph all enviroguards w/c 4 June 2018

Pears Building drop in, 28 June 2018
10 Jun 2018

28 June, 5 to 7pm in the Peter Samuel Hall, Royal Free Hospital

At this drop in there will be displays and people on hand to answer questions about the research that will be conducted in the Institute of Immunity and Transplantation, the construction timeline for the Pears Building and the measures that are being taken to minimise disruption to the local community.

Hoarding plan and timetable
6 Jun 2018

Hoarding plan and timetable

Agenda CWG meeting 26 June 2018
6 Jun 2018

Agenda CWG meeting 26 June 2018

Construction works, weeks commencing 4, 11 and 18 June 2018
5 Jun 2018

Construction look ahead works w/c 4 June 18

Church vibration report graph w/c 28 May 2018
5 Jun 2018

Church Vibration Report Graph w/c 28 May 18

Hospital vibration report graph w/c 28 May 2018
5 Jun 2018

Hospital vibration report graph w/c 28 May 18

Noise report graph all enviroguards w/c 28 May 2018
5 Jun 2018

Noise Report w/c 28 May 18

Dust report graph all enviroguards w/c 28 May 2018
5 Jun 2018

Dust Report w/c 28 May 2018

CWG meetings
29 May 2018

Date for the next CWG meeting: 3 December 2018

The next Construction Work Group meeting is on:

17 September

All welcome

CWG meetings start at 6pm in the Boardroom, Royal Free Hospital . All welcome. If you haven’t attended before, please contact [email protected] to be put on the list for papers.

Dust report graph all enviroguards w/c 14 May 2018
25 May 2018

Dust report graph all enviroguards for w/c 14.05.18

Noise report graph all enviroguards w/c 14 May 2018
25 May 2018

Noise report graph all enviroguards w/c 14.05.18

Hospital vibration report graph w/c 14 May 2018
25 May 2018

Hospital vibration report w/c 14.05.18

Hospital vibration report graph w/c 14 May 2018
25 May 2018

Church vibration report graph w/c 14.05.18

You said we did chart 
25 May 2018

You said, we did (26 June 2018)

Construction works, weeks commencing 8 May 2019
25 May 2018

Construction look ahead works w/c 08.05.18

CWG meeting notes 10 May 2018
10 May 2018

CWG meeting notes 10.05.18

Construction Working Group (CWG) terms of reference 
9 May 2018

Terms for a working group which will operate during the construction of the Pears Building

1. Terms for a working group which will operate during the construction of the Pears Building, a medical research centre being built in the grounds of the Royal Free Hospital from 2018-2020. It will house the UCL Institute of Immunity and Transplantation, a world-class research facility currently located in the main hospital building. This project is a collaboration between the Royal Free London NHS Foundation Trust, the Royal Free Charity and University College London.

2. Members of the group include the Royal Free Charity; Willmott Dixon, the developers; the hospital trust; Hampstead Hill School; St Stephen’s Church; and residents of Pond Street as well as representatives of Camden Council, local councillors, other residents living in the immediate area and local groups representing or working in the local community. There will be an open invitation for any local person or group to attend.

3. The purpose of the group is to provide an open forum between the community and the developers to make sure the works are in accordance with the commitments in Section 106 of the planning permission granted by Camden Council.

4. The group will aim to promote a two-way conversation between those responsible for the development and nearby residents and the wider local community in order to minimise disruption and foster good relations between the organisations involved.

5. The developers will undertake to keep the neighbours of the site and the wider community regularly informed about the progress of the works, to warn of any operations such as demolition or piling that are likely to affect those living close to the site boundary, to explain measures taken to monitor and mitigate disruption, to hear residents’ views on how effective they are and their suggestions for improvements where necessary.

6. Meetings of the group will be held approximately every six weeks and advertised on the charity and trust websites, on the site hoarding and via email to local stakeholders who have asked to be notified. A draft agenda will be published at the same time, at least three weeks before each meeting, and comments invited. A final agenda will be circulated at least a week before the meeting. In the event of an urgent meeting being called, at least a week’s notice will be given.

7. Notes of decisions and key discussion points will be made available within 14 days of the meeting. Agendas, meeting notices and other relevant documents will be published in a designated area on the charity website.

CWG terms of reference

Pears Building – Detailed basement construction plan
20 Mar 2018

The full Detailed Basement Construction plan as submitted to and approved by Camden Council can be accessed here.